3 ways to manage tasks in SharePoint

Posted on March 19, 2016
SharePoint

Let’s face it, Task Management is a core part of any project or day at work for that matter. Every day we have new tasks that come up, get completed or re-assigned to others. In fact, tasks are such a staple of our work, that over the course of my career, I have seen people use any available medium to manage them. From hand-written notes to Excel, Outlook, MS Project or some online “To-Do” type applications. If your organization is using SharePoint, there is a pretty robust task management capability built in. In this blog post I would like to describe 3 ways you can manage tasks in SharePoint. Your choice will be based on personal preference and comfort with technology. Did I mention that this topic is quite dear to my heart since I spent 15 years in Project Management?

Option 1: Manage Tasks in SharePoint using Tasks web part

If you are looking for simple, out of the box, web-based task management, there is already a cool web part available to you that you can use. It is called Tasks. It has been part of SharePoint for a while but in SharePoint 2013 (SharePoint Online/Office 365) it got a major face-lift and technical improvements, like an ability to display tasks on a timeline. The web part can be used right out of the box. You, of course, can customize it with metadata if you wish. For every new task created, you need to fill in the out of the box metadata like task status, priority, start and due dates, etc.

While at the core – it is just like another list in SharePoint with rows and columns containing content and metadata, it also has some specific task management “smart” functionality. For example:

  • By marking Task Status to Completed, it changes % Complete to 100%. And vice versa, by changing % Complete to 100%, it changes Task Status to Completed. So it works just like in MS Project.
  • You can configure the task list to send an email to the individual(s) in the Assigned To column. You can alter that setting in the Advanced Settings of the Tasks Web Part sendemailtask
  • You can create subtasks, just like in MS Project createsubtask
  • And the absolute beauty is the timeline. Sometimes task lists can get pretty complicated and hard for end users to visualize. To help with that, you can add tasks to the timeline that is prominently displayed just above the task list. NOTE: To be able to add tasks to the timeline, user needs to have Edit or above permission level. Users with Contribute permission level will not be able to add tasks to Timeline addtotimeline taskstimeline

How to add Tasks Web Part to SharePoint

  1. To create a Web Part go to Site Contents > Add an App > Tasks Web Part (you need to have Admin privileges to do this) addapptasks
  2. Give it a name, click OK createtasklist
  3. To insert a newly created Task List to the Site homepage, click on Page > Edit > Insert Tab > Web Part > Name of Task List you created. Then click Add (on the right side of the screen). Click Save (to save the page) editpageaddtasklist

 

Pros

  • Web-based interface, no need to need for special software
  • Simple to setup and use
  • Ability to send email notifications when tasks are assigned
  • Ability to create subtasks
  • Ability to add tasks to the Timeline
  • Pre-built views (My Tasks, Late Tasks, Upcoming Tasks, Gantt Chart, etc.)

Cons

  • Not as robust  in terms of functionality as MS Project

Option 2: Manage Tasks in SharePoint using Tasks web part and MS Project

If you are into more serious project management, and SharePoint Tasks web part is not enough, you can use SharePoint Task List in conjunction with the MS Project. You can either open the Task List using MS Project software or synchronize an existing MS Project Schedule with Tasks web part.

How to manage SharePoint Tasks with MS Project

I actually recently published a separate, pretty detailed blog post on how to sync SharePoint Task List and MS Project. Click here to access it

Such a combination allows Project Managers to benefit from advanced functionality of MS Project, such as resource and schedule management, and at the same time allows your team members to access the tasks via web-based, clean user interface (SharePoint Task List).

Pros

  • All of the Pros from Option 1 +
  • Ability to combine flexibility of MS Project with simplicity of SharePoint Task List

Cons

Option 3: Manage Tasks in SharePoint using Outlook

Another cool way to manage SharePoint tasks is by managing them from your Outlook email client. A while back I published a detailed blog post on how to connect SharePoint with Outlook. Usually most users use this feature to sync SharePoint calendars with Outlook calendars. However, as indicated in that same blog post, you can also connect other SharePoint lists, like Tasks, Contacts and even a Discussion Board. Since today we are talking about Tasks, let me explain how to connect SharePoint Task list to Outlook and manage SharePoint tasks from within Outlook.

How to connect SharePoint Task List to Outlook:

  1. Go to the root of your Task List, List Tab > Connect to Outlook connecttooutlook
  2. You will get a prompt, asking you to confirm the connection to Outlook. Click Yes connecttooutlookprompt
  3. Your desktop Outlook application will now open and tasks will synchronize to your Outlook

How to manage SharePoint Tasks from Outlook

  1. Synchronized tasks will appear in the same window as your regular Outlook tasks. They will not be mixed up with your personal tasks. Instead, they will be in the “folder” that will contain the name of the SharePoint site you synchronized them from. Once in Outlook, click on that folder on the left hand-side.
  2. Working with synchronized SharePoint tasks is exactly the same as with “regular” tasks. Just double click the task, make necessary changes and hit Save & Close. The changes will instantly be transmitted back (syncrhonized) to SharePoint Task List modifytask

Pros

  • All of the Pros from Option 1 +
  • Ability to work on tasks without leaving mailbox

Cons

  • Just like with SharePoint-Outlook Calendar sync, it will synchronize the whole task list. So if your Task List contains hundreds of tasks, all of them will be synchronized to your Outlook, which might make it messy for you to navigate through
  • For whatever reason (might be a bug), if task item is assigned to multiple people in SharePoint Task List, it only shows as assigned to 1 person – whoever appears first in the Assigned To field – this might mislead the users.
  • All synchronized SharePoint Tasks appear as a single list of tasks in Outlook. In other words, if you had subtasks (indented tasks) in SharePoint, in Outlook they would look like a regular list of independent tasks. Also, the order of tasks in Outlook might be different from that in SharePoint. So syncing tasks to Outlook might not make sense when you have long and complicated schedules. See below images which capture same task list in SharePoint and Outlook and you will understand what I mean tasklistsharepoint tasklistoutlook